CAD $1,290,990
2010
The work to be prepared includes various piping within two new buildings (Hauled Wastewater and Leachate) and within the existing plant. Our scope of work included the placement of various pumps, boilers, sampling equipment, snowmelt systems, and the replacement of existing sludge pumps. The work also included with sheet metal ductwork, heat recovery ventilators insulation and a Building Management Systems, (BMS).
Newton Mechanical Electrical INC. offers the best products and service in the industry. Contact Us Today! Ph: (204) 415-1052