CAD $10,200,000
2017
The scope of work for this project included the mobilization to site as well as the design, supply and installation of the new packaged water treatment skid. NME also undertook the supply and installation of all miscellaneous piping and electrical to accommodate the new systems. The supply and installation of the Water Treatment Plant building and process equipment was managed and executed by our team as well as the installation of the septic field including the equalization tanks, pumps and piping. Design and installation of the steel structure building was included in the scope of work as well as the commissioning and training of operations sta for the new treatment equipment.